J.J Pickle Federal Building
Renovations Project Informational Site

Announcements

Upcoming/Ongoing Events

​Updated December 9, 2019

  • Fire alarm pre-testing will be performed for the entire building on 12/9 & 12/10 from 4-6am. Final fire alarm testing will be performed on 12/11 & 12/12 at 5 PM. As per the usual practice, a building-wide Fire Alarm testing announcement will precede the actual test and triggering of audio/visual alarms.​

  • All tenants have been returned to their respective floors.  Floor 4 is now a construction zone and elevators are locked out of this floor.  Areas being impacted on Floor 9 are isolated with temporary walls, so elevators continue to service this floor.

  • Construction has begun for Floor #9.  The LBJ historical suite will not be available for the remainder of the project.

  • Floor abatement, carpet/base replacement and painting will be performed on Ground Floor during various weekends in November.  Please see below for locations and specific dates.

  • Construction work hours have been established as 4 AM to 4 PM with noise restrictions being 9 AM to 3 PM (M-F) as previously coordinated with tenants.

  • While GSA is experiencing their own office renovations, the binder containing “Abatement Field Reports” will be kept in the AFG office on the 7th floor.