J.J Pickle Federal Building
Renovations Project Informational Site

Tenant Phasing Schedule

Design Package #1

5th Floor ………………………………… Complete

7th Floor ………………………………… Complete

8th Floor ………………………………… Complete

Penthouse ……………………………… On schedule to complete 12/23/2019

Basement (In Place) ……………… On schedule to complete 12/23/2019

Ground (In Place) …………………… On schedule to complete 12/23/2019

Infrastructure ………………………….. On schedule to complete 12/23/2019

Design Package #2

1st Floor ………………………………….. Complete

2nd Floor ……………………………….. Complete

3rd Floor ………………………………… Complete

6th Floor ………………………………… Complete

4th Floor (Swing) …………………… On schedule to complete 12/12/2019

Design Package #3

9th Floor (In Place) ………..……… On schedule to complete 12/23/2019

LBJ Suite ……………………………….. On schedule to complete 12/23/2019